1) BYRON SHIRE COUNCIL
4.4 - Attachment 2
CONDITIONS OF CONSENT:
Parameters of this Consent
1) Development is to be in accordance with approved plans
The development is to be in accordance with plans listed below:
Plan No. |
Description |
Prepared by |
Dated: |
DA-01 |
Site and Demolition Plan |
Joe Davidson |
January 2016 |
1 |
Floor Plan |
G. Higginson |
22 April 2016 |
2 |
Elevations |
G. Higginson |
22 April 2016 |
3 |
Elevations |
G. Higginson |
22 April 2016 |
4 |
Landscape Plan |
G. Higginson |
22 April 2016 |
The development is also to be in accordance with any changes shown in red ink on the approved plans or conditions of consent.
The approved plans and related documents endorsed with the Council stamp and authorised signature must be kept on site at all times while work is being undertaken.
2) Compliance with Building Code of Australia and insurance requirements under the Home Building Act 1989
(1) For the purposes of section 80A (11) of the Act, the following conditions are prescribed in relation to a development consent for development that involves any building work:
(a) that the work must be carried out in accordance with the requirements of the Building Code of Australia ,
(b) in the case of residential building work for which the Home Building Act 1989 requires there to be a contract of insurance in force in accordance with Part 6 of that Act, that such a contract of insurance is in force before any building work authorised to be carried out by the consent commences.
(2) This clause does not apply:
(a) to the extent to which an exemption is in force under clause 187 or 188, subject to the terms of any condition or requirement referred to in clause 187 (6) or 188 (4), or
(b) to the erection of a temporary building.
(3) In this clause, a reference to the Building Code of Australia is a reference to that Code as in force on the date the application for the relevant construction certificate is made.
3) Erection of signs
(1) For the purposes of section 80A (11) of the Act, the requirements of subclauses (2) and (3) are prescribed as conditions of a development consent for development that involves any building work, subdivision work or demolition work.
(2) A sign must be erected in a prominent position on any site on which building work, subdivision work or demolition work is being carried out:
(a) showing the name, address and telephone number of the principal certifying authority for the work, and
(b) showing the name of the principal contractor (if any) for any building work and a telephone number on which that person may be contacted outside working hours, and
(c) stating that unauthorised entry to the work site is prohibited.
(3) Any such sign is to be maintained while the building work, subdivision work or demolition work is being carried out, but must be removed when the work has been completed.
(4) This clause does not apply in relation to building work, subdivision work or demolition work that is carried out inside an existing building that does not affect the external walls of the building.
(5) This clause does not apply in relation to Crown building work that is certified, in accordance with section 109R of the Act, to comply with the technical provisions of the State’s building laws.
(6) This clause applies to a development consent granted before 1 July 2004 only if the building work, subdivision work or demolition work involved had not been commenced by that date.
Note: Principal certifying authorities and principal contractors must also ensure that signs required by this clause are erected and maintained (see clause 227A which currently imposes a maximum penalty of $1,100).
4) Notification of Home Building Act 1989 requirements
(1) For the purposes of section 80A (11) of the Act, the requirements of this clause are prescribed as conditions of a development consent for development that involves any residential building work within the meaning of the Home Building Act 1989 .
(2) Residential building work within the meaning of the Home Building Act 1989 must not be carried out unless the principal certifying authority for the development to which the work relates (not being the council) has given the council written notice of the following information:
(a) in the case of work for which a principal contractor is required to be appointed:
(i) the name and licence number of the principal contractor, and
(ii) the name of the insurer by which the work is insured under Part 6 of that Act,
(b) in the case of work to be done by an owner-builder:
(i) the name of the owner-builder, and
(ii) if the owner-builder is required to hold an owner-builder permit under that Act, the number of the owner-builder permit.
(3) If arrangements for doing the residential building work are changed while the work is in progress so that the information notified under subclause (2) becomes out of date, further work must not be carried out unless the principal certifying authority for the development to which the work relates (not being the council) has given the council written notice of the updated information.
(4) This clause does not apply in relation to Crown building work that is certified, in accordance with section 109R of the Act, to comply with the technical provisions of the State’s building laws.
5) Development Contributions
Council resolved not to charge Section 94 contributions for secondary dwellings under SEPP (Affordable Rental Housing Policy) 2009 subject to the following requirements:
a) That the maximum size of the secondary dwelling or granny flat does not exceed 60sqm.
b) That the floor space ratio for the whole development of the site does not extend beyond the 0.5:1 and that 25% of the site must be covered by absorbent surfaces such as lawn or landscaping.
c) That the secondary dwelling or granny flat does not increase the overall number of bedrooms on the site to greater than 5.
d) That the applicant has applied for a secondary dwelling or granny flat and specifically advised that the development is not to be used for tourism purposes and accepts a condition of consent to the same effect.
Section 94 Contributions have not been charged on this application based on the above criteria. Should any of the above conditions change your development may be referred to Council's Compliance Department for further action.
The following conditions are to be complied with prior to issue of a Construction Certificate
6) Water and Sewerage - Section 68 approval required
An Approval under Section 68 of the Local Government Act 1993 to carry out water supply work and sewerage work must be obtained.
7) Compliance with Basix Certificate requirements
The development is to comply with Basix Certificate No. 6981141S, dated 20 January 2016. The commitments indicated in the Certificate are to be indicated on the plans submitted for approval of the Construction Certificate.
The plans submitted must clearly indicate all windows numbered or identified in a manner that is consistent with the identification on the Basix Certificate.
Minor changes to the energy efficiency measures may be undertaken without the issue of an amendment under Section 96 of the Act, provided that the changes do not affect the form, shape or size of the building.
Proposed colours must be consistent with the provisions of Section C3.1 of Council’s Development Control Plan 2010. Note that white colours are not permissible.
Such plans and specifications must be approved as part of the Construction Certificate.
8) Long Service Levy to be paid
A Long Service Levy must be paid to the Long Service Payments Corporation. This is a State Government Levy and is subject to change.
These payments may be made online at www.longservice.nsw.gov.au or at Council’s Administration Office, Station Street, Mullumbimby. Where paying to Council, cheques are to be made payable to ‘Byron Shire Council’.
For further information regarding the Long Service Payment please refer to the website above.
9) Site Waste Minimisation and Management Plan
Chapter 1: Part F of Byron Shire Development Control Plan 2010 (DCP 2010) aims to facilitate sustainable waste management in a manner consistent with the principles of Ecologically Sustainable Development. Prior to the issue of a Construction Certificate, a Site Waste Minimisation and Management Plan (SWMMP) must be submitted outlining measures to minimise and manage waste generated during demolition, construction and the ongoing operation and use of the development. The SWMMP must specify the proposed method of recycling or disposal and the waste management service provider.
A template is provided on Council’s website to assist in providing this information www.byron.nsw.gov.au/files/publications/swmmp_-_pro-forma-.doc)
10) Consent required for works within the road reserve
Consent from Council must be obtained for works within the road reserve pursuant to Section 138 of the Roads Act 1993. Three (3) copies of engineering construction plans must accompany the application for consent for works within the road reserve.
Such plans are to be in accordance with Council’s current Design & Construction Manuals and are to provide for the following works:
Driveway (residential areas)
|
A driveway(s) in accordance with Council's current “Northern Rivers Local Government Development Design & Construction Manuals and Standard Drawings”. |
11) Internal Driveway details required
The application for a Construction Certificate is to include plans and specification that indicate vehicular access from the site boundary to the proposed car space(s). Vehicular access must be in accordance with AS 2890.1-2004: Parking facilities, Part 1: Off-street car parking. Plans are to include the following items:
a) pavement description;
b) site conditions affecting the access;
c) existing and design levels;
d) longitudinal section from the road centreline to the car space(s);
NOTE: The plans must be in compliance with Council's current “Northern Rivers Local Government Development Design & Construction Manuals and Standard Drawings”.
12) Flood Planning Level for new buildings
The flood planning level for this development is 5.0m A.H.D. The plans and specifications to accompany the construction certificate application are to indicate a minimum habitable floor level that is at or above the flood planning level.
The plans and specifications to accompany the construction certificate application are also to indicate the use of flood compatible materials and services below the flood planning level in accordance with the requirements of Council’s Development Control Plan 2014 – Chapter C2 – Areas Affected by Flood.
13) Certificate of Compliance from Rous Water required – Water Management Act 2000
A Certificate of Compliance from Rous Water is to be obtained confirming that all money payable to Rous Water in respect to the load the development imposes on the Regional Bulk Water Supply has been paid.
Note: Byron Shire Council acts as Rous Water’s agent in this matter and will issue a Certificate of Compliance on behalf of Rous Water upon payment of the Rous Water Development Servicing Charge to this Council. The charge is calculated as the Rous Water Development Servicing Charge per Equivalent Tenement current at the time of payment multiplied by the assessed number of ET’s for the development for water supply purposes. For further information about the Regional Bulk Water Supply Development Servicing, please contact Rous Water on (02) 6621 8055 or water@rouswater.nsw.gov.au .
Copies of the application forms for Certificates of Compliance are available on Council’s website http://www.byron.nsw.gov.au/files/Forms/Section_305_Certificate.pdf or from Council’s Administration Office. Copies of Byron Shire Council’s Development Servicing Plans are available at Council’s Administration Office.
14) Building materials and colours to be specified
i. Walls are to be constructed from weathertex cladding “Heritage’ (or similar),
ii. Roof is to be constructed from colourbond.
iii. Colours are to match the existing dwelling onsite.
Such plans and specifications must be approved as part of the Construction Certificate.
The following conditions are to be complied with prior to commencement of building works
15) Plumbing Standards and requirements.
All Plumbing, Water Supply, Sewerage and Stormwater Works shall be installed in accordance with the Local Government Act 1993, Plumbers Code of Australia and AS/NZS 3500 Parts 0-5, the approved plans (any notations on those plans) and the approved specifications. The changes made are from Plumbers and Drainage Regulation 2012 NSW Government.
a) The licensee is to provide 24 hours notice and attend the site for the following INSPECTIONS, prior to covering of work. Inspections will be carried out a mutually convenient time:
i) Pre-start and Sediment Control;
ii) Internal Drainage;
iii) External Drainage;
iv) Water Rough In;
v) Fire Services;
vi) Stackwork;
vii) Final - all work completed. - * Note below.
b) A licensee is required to provide to Council and owner of the property after completion of the work and within 48 hours, a Compliance Certificate and Sewer Services Diagram/ Works as Executed drawings.
Note: Council will send each plumber proformas of these documents when the Notice of Work permit has been issued by Council to allow the plumber to commence work.
16) Erosion and sediment measures
Where erosion of soils or runoff of any substance is likely to occur, erosion and sedimentation controls are to be in place in accordance with the Guidelines for Erosion & Sediment Control on Building Sites. This may include stockpiled materials such as sand, etc.
Any such measures that are deemed to be necessary because of the local conditions must be maintained at all times until the site is made stable (i.e. by permanent vegetation cover or hard surface).
The following conditions are to be complied with during construction
17) Construction times
Construction works must not unreasonably interfere with the amenity of the neighbourhood. In particular construction noise, when audible from adjoining residential premises, can only occur:
a) Monday to Friday, from 7 am to 6 pm.
b) Saturday, from 8 am to 1 pm.
No construction work to take place on Saturdays and Sundays adjacent to Public Holidays and Public Holidays and the Construction Industry Awarded Rostered Days Off (RDO) adjacent to Public Holidays.
Note: Council may impose on-the-spot fines for non-compliance with this condition.
18) Construction Noise
Construction noise is to be limited as follows:
a) For construction periods of four (4) weeks and under, the L10 noise level measured over a period of not less than fifteen (15) minutes when the construction site is in operation must not exceed the background level by more than 20 dB(A).
b) For construction periods greater than four (4) weeks and not exceeding twenty‑six (26) weeks, the L10 noise level measured over a period of not less than fifteen (15) minutes when the construction site is in operation must not exceed the background level by more than 10 dB(A)
Note: Council may impose on-the-spot fines for non-compliance with this condition.
19) Builders rubbish to be contained on site
All builders rubbish is to be
contained on the site in a ‘Builders Skips’ or an enclosure. Footpaths, road
reserves and public reserves are to be maintained clear of rubbish, building
materials and all other items.
20) Demolition
Any required demolition works must be undertaken in accordance with the relevant requirements of Australian Standard AS 2601–1991: The Demolition of Structures published by Standards Australia, and the WorkCover Authority of NSW.
The following conditions are to be complied with prior to issue of a Final Occupation Certificate
21) Works to be completed prior to issue of a Final Occupation Certificate
All of the works indicated on the plans and approved by this consent, including any other consents that are necessary for the completion of this development, are to be completed and approved by the relevant consent authority/s prior to the issue of a Final Occupation Certificate.
Any Security bond paid for this application will be held until Council is satisfied that no further works are to be carried out that may result in damage to Councils road/footpath reserve.
22) Stormwater disposal
Stormwater must be collected and disposed of in a controlled manner such that stormwater flows are:
a) Clear of buildings and infrastructure,
b) Not concentrated so as to cause soil erosion, and
c) Not onto adjoining land.
23) Floor Levels – Certification for Flooding
Prior to the issue of an Occupation Certificate, a certificate from a registered surveyor must be submitted to the Principle Certifying Authority confirming the height of habitable and non-habitable floors. An Occupation Certificate must not be issued unless the floor levels are at or above the relevant flood planning levels.
The following conditions are to be complied with at all times
24) No subdivision - Secondary Dwelling
In accordance with clause 24 of the State Environmental Planning Policy (Affordable Rental Housing) 2009, subdivision of the subject land is not to occur.
25) Relationship to Principal Dwelling
The secondary dwelling must remain on the same lot as the principal dwelling.
26) Use of Secondary Dwelling
The secondary dwelling is not approved for holiday letting and/or for the use as a tourist facility.
27) No more than the principal dwelling and secondary dwelling
There must not be any dwelling on the land other than the principal dwelling and the secondary dwelling.
28) Flood Evacuation Plan
A copy of the approved flood evacuation plan is to be laminated in clear plastic and displayed in a prominent location within the development (e.g. Kitchen, office).